Week 1

01/23/2025 - Group Meeting (30 minutes)

  • Made a team Google Drive

  • Brainstormed an introduction email

Week 2

01/28/2025 - Client Meeting (1 hour)

  • Met client in person for the first time

  • Showed current progress on the project

  • Brief breakdown of what he hopes for us to accomplish

  • Joined the project's discord

01/30/2025 - Group Meeting (30 minutes)

  • Code review session

  • Initial thoughts are to start from scratch

  • Utilize VueJS

  • There are enough bugs, so using existing code seems concerning

  • There are good building blocks

  • Aren is making a slideshow linking pieces of code

  • Confused by the use of Firebase

  • Set up Jira group

  • Still waiting on stuff from the client

Week 3

02/05/2025 - Group Meeting (30 minutes)

  • Be honest that the initial timeline would be tough to achieve

  • The first thing to fix is the bugs (both applications)

  • Rebase and determine how we want to approach the map editor

  • After clarifications at the meeting tomorrow, we can have a better idea of an approach

  • Next group meeting, we should...

  • Set up Jira sprint tasks

  • Divvy up the bugs to fix

02/06/2025 - Client Meeting (1 hour)

  • Given the OK to utilize AI to understand the code

  • Merge Map Editor and mapstructor.org together

  • Completed after developing the editor and fixing bugs in mapstructor.org

  • Then, deploy to the live site (nahc site)

  • Discussed the bugs

  • Filled out timeline

  • Given access to MongoDB

Week 4

02/13/2025 - Client Meeting (1 hour)

  • Went through all the bugs

    • Updated client on how many were complete already

  • Examined remaining bugs and assigned some to members

    • Adjusted timeline for fixing bugs

02/14/2025 - TA Meeting (30 minutes)

  • Met our TA for the first time

  • Gave the TA some history and background of the project

  • Shared the bugs we fixed and some we are working on

  • Explained our strategy for the next couple of weeks

Week 5

02/20/2025 - Client Meeting (1 hour)

  • Went through current progress

  • Talked about more bugs that have appeared

  • Cannot have multiple people logged into the editor at the same time

Week 6: DEMO WEEK

02/27/2025 - Client Meeting (1 hour)

  • Went through completed bugs from the past week and demoed them

  • Attempted to fix another by reuploading the data to see if the layer appears

  • Began some discussion about Map Editor plans

  • Got some drawings to start planning

  • Planned a virtual meeting for next week

02/28/2025 - TA Meeting (30 minutes)

  • Shared each person's progress for the past 2 weeks

  • Came up with goals for the next 2 weeks

Week 7

03/04/2025 - Client Meeting (1 hour)

  • Fixed the bug regarding layers not loading

    • An earlier solution was causing the problem

  • Planned out the final preparations for the debugging phase of the project

Week 8

03/11/2025 - Client Meeting (2 hours)

  • Gave some updates on where things are at with the project

  • Clarified that identical CSS is more important than a new feature

  • Walked through the whole project structure and how to do stuff

  • Assisted Nitin with updating the paint for a certain layer

03/13/2025 - TA Meeting (30 minutes)

  • Shared our progress so far

  • Discussed concerns about the project

  • Evaluated if we had enough work remaining for everyone

Week 9: SPRING BREAK

  • No work

Week 10

03/27/2025 - Client Meeting (1 hour)

  • Gave an update on the progress of the bugs

  • Discussed plans moving forward

    • Halt work on bugs

    • Start the new project on creating maps

      • Copy the necessary code from the MENY project

      • Add in a few layers to show it working

      • Give an explanation of how to deploy a blank instance of the site to a domain

Week 11

04/01/2025 - Client Meeting (1 hour)

  • Went through making a map

  • Clarified that we want all features of MENY in the new instances

  • Discussed the possibility of deploying copies of the site to different subfolders and domains

04/03/2025 - TA Meeting (30 minutes)

  • Discussed what features we've completed and what we are working on currently

  • Plan to clarify with the client what the goal is for the semester

04/03/2025 - Client Meeting (1 hour)

  • Finished the process of making a map and uploading it to the MENY site

  • TOP PRIORITY is the blank instance of MENY

  • When clicking "Add Layer" or "Add Standalone Layer", it pops up with different options

Week 12: DEMO WEEK

04/10/2025 - Client Meeting (1 hour)

  • Went through the current state of the project

  • How the blank instance is coming along

    • globalwebmapper MapBox stuff is still having an issue displaying

  • Progress we've made with drawing tools

  • The client looked through instructions for making a blank instance

    • He wants a video demoing how to make a blank instance, make mapstructor.org

  • His partner wants viewing North America - Landowners to be password protected for viewing the data

  • Timeline should be updated to wait to update land until released

  • Continue development on drawing tools

Week 13

04/17/2025 - Client Meeting (1 hour)

  • Went through the current state of the project

    • 2 different group members solved different halves of the drawing issue

    • Making some progress on the timeline update

    • Blank instances are complete

  • No glaring issues with globalwebmapper stuff

    • Try it again and give it some time to load?

Week 14

04/25/2025 - TA Meeting (30 minutes)

  • Shared what individual contributions each member made for Demo 2

  • Updated TA on website progress

Week 15

05/01/2025 - Client Meeting (1 hour)

  • Drawing features are reasonably acceptable

    • Need to be able to add information to the drawn layers (Seth not present, so unsure about progress with that)

  • Documentation has been updated for the next group

  • Updated prisma stuff with Vercel so the generated files are no longer included in the project

  • Discussed our demo time and invited the client to the presentation

  • Wants us to document whatever bugs/remaining development for the next group

  • Halt coding new features, just finish up what we were working on and move to transition period

Week 16: DEMO WEEK

NO MEETINGS - End of Project